Project Milestones

Milestone dan progres tiap proyek

Tangki BBM 16KL - Pertamina

40.0%
40%
Design Approval
10%Completed
Material Procurement
15%Completed
Fabrication 50%
25%In Progress
Fabrication Complete
25%Pending
Final Inspection & Delivery
25%Pending

Truk Tangki Kimia 10KL - AHM

21.0%
21%
Engineering Release
15%Completed
Chassis Assembly 1st Unit
20%In Progress
All Units Completed
40%Pending
Delivery
25%Pending
ProjectMilestoneWeightTarget DateActual DateCompletionPICStatus
PRJ001Design Approval10%2026-09-012026-09-03
100%
Eko EngineeringCompleted
PRJ001Material Procurement15%2026-09-202026-09-25
100%
Hadi ProcurementCompleted
PRJ001Fabrication 50%25%2026-10-31—
60%
Supri ProductionIn Progress
PRJ001Fabrication Complete25%2026-11-30—
0%
Supri ProductionPending
PRJ001Final Inspection & Delivery25%2026-12-31—
0%
Reza PMPending
PRJ002Engineering Release15%2026-10-152026-10-14
100%
Eko EngineeringCompleted
PRJ002Chassis Assembly 1st Unit20%2026-11-30—
30%
Supri ProductionIn Progress
PRJ002All Units Completed40%2027-02-28—
0%
Supri ProductionPending
PRJ002Delivery25%2027-03-31—
0%
Sinta PMPending