Project Milestones
Milestone dan progres tiap proyek
Tangki BBM 16KL - Pertamina
40.0%40%
Design Approval
10%Completed
Material Procurement
15%Completed
Fabrication 50%
25%In Progress
Fabrication Complete
25%Pending
Final Inspection & Delivery
25%Pending
Truk Tangki Kimia 10KL - AHM
21.0%21%
Engineering Release
15%Completed
Chassis Assembly 1st Unit
20%In Progress
All Units Completed
40%Pending
Delivery
25%Pending
| Project | Milestone | Weight | Target Date | Actual Date | Completion | PIC | Status | |
|---|---|---|---|---|---|---|---|---|
| PRJ001 | Design Approval | 10% | 2026-09-01 | 2026-09-03 | 100% | Eko Engineering | Completed | |
| PRJ001 | Material Procurement | 15% | 2026-09-20 | 2026-09-25 | 100% | Hadi Procurement | Completed | |
| PRJ001 | Fabrication 50% | 25% | 2026-10-31 | — | 60% | Supri Production | In Progress | |
| PRJ001 | Fabrication Complete | 25% | 2026-11-30 | — | 0% | Supri Production | Pending | |
| PRJ001 | Final Inspection & Delivery | 25% | 2026-12-31 | — | 0% | Reza PM | Pending | |
| PRJ002 | Engineering Release | 15% | 2026-10-15 | 2026-10-14 | 100% | Eko Engineering | Completed | |
| PRJ002 | Chassis Assembly 1st Unit | 20% | 2026-11-30 | — | 30% | Supri Production | In Progress | |
| PRJ002 | All Units Completed | 40% | 2027-02-28 | — | 0% | Supri Production | Pending | |
| PRJ002 | Delivery | 25% | 2027-03-31 | — | 0% | Sinta PM | Pending |