Work Orders
Work order per operasi dan unit
| Code | Serial | Operation | Seq | Work Center | Assigned To | Target | Est.h | Act.h | Eff% | Status | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| WO-2026-001 | SN-TK-001 | Fit Up & Welding | 30 | WC-WELD | Budi Welder | 2026-10-10 | 40h | 42h | 95% | Completed | |
| WO-2026-002 | SN-TK-001 | NDT / Radiography | 40 | WC-QC | QC Andi | 2026-10-12 | 8h | 7h | 114% | Submitted for QC | |
| WO-2026-003 | SN-TK-002 | Fit Up & Welding | 30 | WC-WELD | Roni Welder | 2026-10-20 | 40h | 22h | 182% | In Progress | |
| WO-2026-004 | SN-TT-001 | Chassis Preparation | 10 | WC-MACH | Heri Mechanic | 2026-10-25 | 8h | 9h | 89% | Completed | |
| WO-2026-005 | SN-TT-001 | Tank Fabrication | 20 | WC-WELD | Budi Welder | 2026-11-10 | 30h | 12h | 250% | In Progress |